How long does it take to make a tension structure?
The time it takes to build a tensioned membrane structure depends upon the material, size and scope of the project. Historically, it takes anywhere from five (5) to twelve (12) months to complete a tension structure project. A typical tension structure schedule of events includes, but is not limited to:
SCHEDULE OF WORK
(3) Weeks for 3D design drawings from time of approved contract terms and receipt of deposit
(3) Weeks for engineering analysis and calculations from time of design approval
(3) Weeks for stamped engineering report and drawings after completion of engineering analysis
(2) Weeks for field measurements from time of footing completion
(2) Weeks for shop drawings after field measurements are surveyed
(2) Weeks to order and receive materials after completion of shop drawings
(4) Weeks to fabricate frame and fabric membrane after receipt of materials
(1) Week to paint frame after its fabrication is complete
(2) Weeks to deliver and install frame and fabric membrane
(22) Weeks Total*
________________
*Schedule is based on
a medium sized project. Additional lead time may be required for:
• Large projects (over 4,000 square foot)
• Customer’s desire to negotiate contract terms
• Customer’s approval time of design drawings
• Possible design revisions due to engineering requirements
• Permitting authorities time to review and approve project
• Possible coordination with schedules of other subcontractors on site
• Acquisition for any specialty materials that are uncommon and not stocked locally
• Delivery to any site outside the vicinity of Southern California and the South West Region